How to Mix Concrete by Hand or in a Mixer
Mixing your own concrete from cement, sand and gravel is cheaper than buying pre-mixed bags and easier than it looks. What makes the difference between strong concrete and crumbly concrete is measuring consistently, mixing thoroughly and using no more water than you need. Here is how to do it by hand or with a mixer.
Before you start: mix it yourself, or not?
- A few post holes or a small repair: pre-mixed bags are simplest. The concrete calculator tells you how many.
- A path, shed base, steps or a small patio: mixing your own from cement and aggregate is cheapest. The concrete mix ratio calculator gives the bags of cement, the sand and gravel (or all-in ballast) and a starting amount of water.
- More than about a cubic yard (0.75 m³): consider ready-mixed concrete from a truck. Mixing that much by hand takes a full day, and the first batches start to stiffen before the last are placed.
What you will need
- Portland cement (94 lb bags in the US, 25 kg bags in the UK), kept dry and off the ground
- Concrete sand (US) or sharp sand (UK) and gravel — or all-in ballast, which is both premixed
- Clean water from a hose or buckets
- A cement mixer, or a sturdy wheelbarrow or mixing board (a sheet of plywood about 4 × 4 ft or 1.2 × 1.2 m)
- A square-mouthed shovel and a mixing hoe or rake
- Two or three buckets of the same size for measuring
- Waterproof gloves, eye protection and a dust mask
Safety: wet cement is strongly alkaline and can cause serious skin burns that you may not feel until hours later. Wear gloves, long sleeves and eye protection, wash any splashes off straight away, and change out of clothing soaked with wet concrete.
1. Choose the mix and measure by the bucket
Concrete ratios are parts by volume — cement, then sand, then gravel. Most slabs, patios and bases use a general 1 : 2 : 3 mix (or 1 : 4 cement to all-in ballast); steps and driveways need a stronger mix, and footings can use a slightly leaner one. The mix ratio calculator lists the common mixes and works out the totals for your job.
Use the same bucket for every material and level it off each time. For a 1 : 2 : 3 batch, that is one bucket of cement, two of sand and three of gravel. Shovelfuls are much less consistent, because a shovel holds more damp sand than loose gravel. Count the buckets out loud — it is easy to lose track halfway through a long day.
2. Mixing by hand
- Mix the dry materials first. Tip the sand and gravel (or ballast) onto the board or into the barrow, add the cement on top, and turn the pile over with the shovel at least three times, until it is one even grey colour with no streaks of sand or cement.
- Make a crater. Hollow out the centre of the pile into a well.
- Add water a little at a time. Pour some into the crater and pull the dry mix from the edges into the water. Keep turning and chopping the mix with the shovel or hoe, adding small amounts of water, until it is evenly wet throughout.
- Check the consistency (see below) and stop adding water as soon as it is workable.
Mix in batches you can place in well under an hour — sooner in hot weather. A full wheelbarrow is heavy to mix and to push; half to two-thirds full is plenty.
3. Mixing in a cement mixer
- Set the mixer up on firm, level ground close to where the concrete is going, with the drum tilted at about 45°.
- With the drum turning, add about half the water and half the gravel. The stones scour the drum and stop cement sticking to it.
- Add the cement, then the sand, then the rest of the gravel, a bucket at a time.
- Add the remaining water gradually until the mix tumbles off the blades cleanly. Let it mix for about 3 minutes after the last material goes in.
- Tip it into a wheelbarrow and start the next batch straight away, so the drum never dries out.
Never reach into a turning drum with your hand or a shovel. At the end of the day, run a few shovelfuls of gravel and a bucket of water in the drum for a few minutes to scour it clean.
How wet should concrete be?
Good concrete is like thick porridge or oatmeal: it holds its shape when you slice through it with the shovel, and the ridges you make with the back of the shovel stay put without slumping or weeping water. As a guide, the water needed is about half the weight of the cement — roughly 12 litres per 25 kg bag, or 5½ US gallons per 94 lb bag — but damp sand already holds water, so you will usually need less.
| What you see | What it means | What to do |
|---|---|---|
| Dry, crumbly, will not hold together | Too little water | Add a little water and keep mixing |
| Holds a sliced edge, ridges stay put | About right | Use it |
| Slumps flat, water pools on top | Too much water — weaker and prone to cracking | Add more dry materials in the same ratio, not cement alone |
It is tempting to add extra water to make concrete easier to spread, but every extra bucket weakens it and makes it shrink and crack more as it dries. Getting the consistency right is more important than getting the ratio exact.
4. Place and compact it
Tip the concrete into the formwork, starting at the far end, and spread it slightly higher than the forms. Work a shovel or a length of timber up and down through it, especially along the edges and corners, to release trapped air, then tap the outside of the forms. Level it by dragging a straight board across the top of the forms in a sawing motion, and finish with a float. Our guide on planning a concrete patio covers formwork, falls and finishing in more detail.
5. Cure it slowly
Concrete hardens by a chemical reaction with water, not by drying out, so keep it damp for at least the first few days — ideally a week. Cover it with plastic sheeting, or mist it with water several times a day in warm weather.
- Light foot traffic: usually after 24–48 hours.
- Cars and heavy loads: wait at least a week, longer in cool weather. Concrete reaches its design strength after about 28 days.
- Cold weather: do not mix or pour when the temperature is below about 40 °F (5 °C) or frost is forecast, unless you can protect the concrete. Concrete that freezes before it hardens is permanently weakened.
- Hot weather: work early or late in the day, keep the materials in the shade, and dampen the base before pouring so it does not draw water out of the mix.
Clean up before it sets
Wash tools, the barrow and the mixer as soon as you finish, while the concrete is still soft. Do not wash cement slurry into drains, gutters or watercourses: it can block pipes and harms wildlife. Rinse onto a patch of hardcore or into a hole you can fill in later.
Common mistakes
| Mistake | Result |
|---|---|
| Too much water | Weak, dusty surface; shrinkage cracks |
| Not mixing the dry materials first | Streaky concrete with weak pockets |
| Soft building sand instead of sharp or concrete sand | Weak concrete that cracks |
| Measuring by shovelfuls | Batches of different strength and colour |
| Letting it dry out in the first days | Surface cracking, lower strength |
| Damp or lumpy cement | Cement that has started to set — do not use it |
Building steps? The concrete steps calculator works out the volume for a whole flight, including a landing at the top.