How to use the paver calculator
- Choose pavers or block paving (laid on sand) or patio slabs (laid on a mortar bed).
- Enter the length and width of the patio, or its total area if it is an irregular shape.
- Enter the size of one paver or slab and the joint between them. Most concrete pavers have spacer nibs, so the joint is 0; slabs usually have 8–10 mm (⅜ in) joints.
- Set the depth of the compacted sub-base and the bedding layer. The defaults suit a garden patio or path.
The paver formula
Pavers = area ÷ ((length + joint) × (width + joint)) × (1 + extra) Sub-base = area × depth × 1.15 (15% for compaction) Bedding = area × depth × 1.10 (10% for screeding) Mortar = 1 part cement : 4 parts sharp sand
Weights use 2,100 kg/m³ for crushed-stone base and 1,600 kg/m³ for sand. Dry sand and cement bulk up about 27% before mixing, which the mortar figures allow for.
Worked example (US)
A 12 × 10 ft patio is 120 ft². Standard 4 × 8 in pavers need 4.5 per ft², so 540 pavers — 567 with 5% extra. A 4 in gravel base is 40 ft³, or 46 ft³ (1.7 yd³) with 15% for compaction: about 3 tons. A 1 in sand bed is 10 ft³, or 11 ft³ with 10% extra — 22 bags of 0.5 ft³.
Worked example (UK)
A 4 × 3 m patio is 12 m². Block paving at 200 × 100 mm needs 50 per m², so 600 blocks — 630 with 5% extra. A 100 mm MOT Type 1 sub-base is 1.38 m³ with compaction, about 2.9 tonnes (4 bulk bags), and a 40 mm sharp sand bed is about 0.84 tonnes (1 bulk bag). Lay 600 × 600 mm slabs with 10 mm joints instead and you need 34 slabs, with a 40 mm mortar bed of 8 × 25 kg bags of cement and 0.86 tonnes of sharp sand.
Common paver and slab sizes
| Size | Typical use | Per ft² | Per m² |
|---|---|---|---|
| 4 × 8 in (100 × 200 mm) | Brick pavers, block paving | 4.5 | 50 |
| 6 × 6 in | Square pavers | 4 | 43 |
| 6 × 9 in | Interlocking pavers | 2.67 | 29 |
| 12 × 12 in | Patio pavers | 1 | 10.8 |
| 24 × 24 in / 600 × 600 mm | Patio slabs | 0.25 | 2.7–2.8 |
| 450 × 450 mm | UK patio slabs | 0.46 | 4.9 |
| 900 × 600 mm | Large-format porcelain or stone | 0.17 | 1.9 |
Figures exclude joints. Wider joints mean slightly fewer slabs, which the calculator allows for.
Base and bedding depths
| Project | Sub-base | Bedding |
|---|---|---|
| Garden path or patio | 4–6 in (100–150 mm) | 1 in sand (25–40 mm) |
| Patio slabs on mortar | 4 in (100 mm) | 1–1½ in mortar (25–40 mm) |
| Driveway | 8 in+ (150–200 mm+) | 1 in sand (25–40 mm) |
Pouring concrete instead? Use the concrete calculator. For a loose gravel area, the gravel calculator works out the stone.
Planning a whole patio? The patio calculator adds the digging, soil to remove, membrane, jointing sand and edging to the same list.
Frequently asked questions
How many pavers do I need per square foot?
Divide 144 by the paver’s face area in square inches. Standard 4 × 8 in pavers need 4.5 per ft², 6 × 6 in pavers 4 per ft², 6 × 9 in pavers 2.67 per ft² and 12 × 12 in pavers 1 per ft². In the UK, 200 × 100 mm block paving needs 50 blocks per m². Add 5% for cuts, or 10% for herringbone and curved edges.
How much gravel and sand do I need under pavers?
For a patio or path, lay 4–6 inches (100–150 mm) of compacted crushed-stone base — crusher run or ¾-inch minus in the US, MOT Type 1 in the UK — topped with about 1 inch (25–40 mm) of bedding sand. Driveways need a thicker base, typically 8 inches (150–200 mm) or more, and more again on soft clay or where the ground freezes.
Should patio slabs be laid on sand or mortar?
Interlocking pavers and block paving are laid on screeded sharp sand and compacted, so the joints lock them together. Larger patio slabs and natural stone are usually laid on a full bed of mortar — about 4 parts sharp sand to 1 part cement — so they do not rock or sink. Avoid laying slabs on five dabs of mortar, which leaves hollows that crack and collect water.
How much area does a ton of base gravel cover?
A US ton of crushed-stone base (about 2,100 kg/m³) covers roughly 40 ft² at 4 inches deep once compacted. A metric tonne of MOT Type 1 covers about 4 m² at 100 mm. Order 10–20% more than the finished volume, because the base compacts when you roll or plate it.
How much extra paving should I buy?
Allow 5% extra for a simple rectangle in a straight or stretcher bond, and 10–15% for herringbone, diagonal layouts, curves or lots of edges to cut around. Buying all your pavers from the same batch also avoids colour differences between pallets.